Explainer
How to track time across multiple job sites
By the TrackBadges team · Updated · 6 min read
The short answer
To track time across multiple job sites, record when each worker starts and stops, stamped with where it happened, and keep travel between sites on the clock. Under 29 CFR 785.38, driving from one job site to another during the workday is hours worked and must be paid. The ordinary commute from home to the first site and back home from the last generally isn't.
Key takeaways
- Travel between job sites during the workday is paid work time (29 CFR 785.38).
- The normal commute from home to the first site, and home from the last, generally isn't (29 CFR 785.35).
- If workers must meet at the shop or yard first, the workday starts there and the drive to the site is paid.
- Punching out and in at each site shows hours per site, but the drive time in the gaps still has to be paid.
- Location-stamped punches show where time was spent; they aren't the same as job costing.
Do you have to pay travel time between job sites?
Yes. Under the Fair Labor Standards Act, travel that's part of the day's work counts as hours worked. 29 CFR 785.38 puts it directly: time spent in travel as part of an employee's principal activity, "such as travel from job site to job site during the workday, must be counted as hours worked."
The same section covers the morning meet-up. If you require workers to report to a shop, yard or meeting place to get instructions, pick up tools or load a truck, the trip from there to the job site is part of the day's work "regardless of contract, custom, or practice." Once the workday has started, the clock keeps running until the last work task is done.
Commute vs. work travel
The line is the start and end of the workday. Travel before the first work task and after the last one is commuting. Everything in between is work.
| Trip | Paid under federal law? | Rule |
|---|---|---|
| Home to the first job site (normal commute) | Generally no | 29 CFR 785.35 |
| Shop or yard to the job site, after loading tools or getting instructions | Yes | 29 CFR 785.38 |
| One job site to another during the day | Yes | 29 CFR 785.38 |
| Last site back to the shop to drop off the truck or tools | Usually yes, when the stop is required work | Still part of the workday |
| Last site, or the shop, to home | Generally no | Ordinary home-to-work travel |
| A one-day trip to another city | Yes, minus the normal commute and meal time | 29 CFR 785.37 |
| Driving a company vehicle home, within the normal commuting area | Generally no, if agreed between employer and employee | Portal-to-Portal Act, 29 U.S.C. 254(a) |
State law can count more travel as work. In California, for example, time spent on transportation the employer requires, such as a mandatory company bus to a remote site, is generally hours worked (Morillion v. Royal Packing Co., 2000). Check your state's rules.
One daily punch or a punch at each site?
Clock in once when the workday starts and once when it ends, and the travel in between is paid automatically. Punch at each site and you can see hours per site, but you have to add the drive time back yourself.
| Approach | How it works | Good for | Watch out for |
|---|---|---|---|
| One punch in, one out per day | Crew clocks in at the yard or first site and out at the end of the day | Payroll; crews that move together | You can't see hours per site |
| A punch at each site | Scan out leaving site A, scan in arriving at site B | Billing clients per site; proving time on site | The gaps between sites are drive time and still have to be paid |
| Stay on the clock and switch jobs | One continuous shift, with the job changed in an app | Job costing by site and task | Needs job codes, and every switch has to be recorded |
The second approach catches a lot of employers out. If the crew scans out at 11:00 at site A and in at 11:20 at site B, those 20 minutes are paid work time even though no clock was running. Either add travel as its own line on the timesheet, or use the first approach.
Worked example: a three-stop landscaping day
Here's one worker's day on a landscaping crew that meets at the yard:
| Time | What's happening | Paid? |
|---|---|---|
| 6:40 to 7:00 am | Drive from home to the yard | No (commute) |
| 7:00 to 7:20 am | Load the truck at the yard | Yes |
| 7:20 to 7:45 am | Drive from the yard to site A | Yes |
| 7:45 to 11:00 am | Work at site A | Yes |
| 11:00 to 11:20 am | Drive from site A to site B | Yes |
| 11:20 to 11:50 am | Lunch at site B, fully off duty | No |
| 11:50 am to 3:10 pm | Work at site B | Yes |
| 3:10 to 3:30 pm | Drive from site B back to the yard | Yes |
| 3:30 to 3:50 pm | Unload and park the truck | Yes |
| 3:50 to 4:10 pm | Drive home | No |
Paid time is 7:00 to 11:20 (4 hours 20 minutes) plus 11:50 to 3:50 (4 hours), for 8 hours 20 minutes, or 8.33 hours. If only the time on site were recorded (7:45 to 11:00 and 11:50 to 3:10), the timesheet would show 6 hours 35 minutes, which is 1 hour 45 minutes short every day.
Over a five-day week that's 8.75 missing hours per worker. Because the true week is 41.67 hours, 1.67 of those missing hours are overtime at time and a half. Convert minutes with the minutes to decimal tool, or total the week with the timesheet calculator.
The simplest fix is for the crew lead to clock everyone in at the yard at 7:00 and out at the yard at 3:50, with a scan out and back in for lunch.
What location-stamped punches tell you
A location-stamped punch records where a clock-in or clock-out happened. There are two common kinds of stamp:
- The scanner's assigned location. A tablet at the yard, or a phone assigned to "Site A," labels every punch it makes with that place.
- A GPS stamp. The device's position at the moment of the scan.
Together they answer "where was this person when they clocked in?" They don't show where anyone went between punches. That takes continuous GPS tracking, which some employers use for drivers and which raises more privacy questions. A geofence is a different thing again: a virtual boundary around a site that blocks or flags punches made outside it.
Job costing: what tracking time by location can't do
Hours by location tell you how long a crew spent at each site, which is often enough to bill a client or check a bid on a small job. They don't tell you what the crew did there. If you need hours by phase or task, like framing versus drywall on job 2041, you need a time clock with job or cost codes and a habit of switching codes when the task changes. Cost codes are more precise, but every switch is one more thing for someone to record. Decide which you need before you choose a tool; time clock apps for construction compares options built for crews.
Setting up time tracking across sites
- Decide what you need per site: payroll only, client billing or job costing.
- Pick a punch approach from the table above and write it down.
- Put a scanner, or a crew lead with a phone, wherever crews start work.
- Label every scanner with its location, and turn on GPS stamps if you want a record of where each scan happened.
- Write a travel pay policy: when the workday starts, and that site-to-site driving is paid.
- Review the gaps between punches each week before you approve hours.
For the broader picture, see how to track employee hours.
Where TrackBadges fits
TrackBadges is built for crews that start together. The crew lead scans each worker's printed badge with their phone at the yard or first site, and again at the end of the day, so drive time between sites stays on the clock. Every punch records the time, the scanner, the scanner's location and, if you turn it on, a GPS stamp of where the scan happened. Scanners and locations are unlimited on every plan.
Be clear about the limits. TrackBadges tracks locations, not job or cost codes, so if you need hours by task, choose a tool that has them. And a solo worker who goes to a different site alone each day, with nobody to scan their badge, is better served by a GPS app on their own phone.
Frequently asked questions
Do you have to pay employees for driving between job sites?
Yes. Under 29 CFR 785.38, travel from job site to job site during the workday is hours worked and must be paid, including any overtime it creates. That's true even if workers drive their own vehicles.
Is the drive from home to the first job site paid?
Generally no. Ordinary travel from home to work is a normal commute and isn't hours worked under federal law, whether the employee works at a fixed location or at different job sites (29 CFR 785.35). Some state rules are broader.
Do I have to pay for time at the shop before going to the site?
Yes, if employees are required to report there to get instructions, load tools or pick up a truck. That work starts the workday, so the time at the shop and the drive from there to the job site are both paid (29 CFR 785.38).
Is driving a company truck home considered work time?
Generally not, if the trip is within the normal commuting area and the employer and employee have agreed to the vehicle use (Portal-to-Portal Act, 29 U.S.C. 254(a)). If the employee does work on the way, like picking up materials, that changes the answer.
How do I track hours for an employee who works at several locations in a day?
Either clock them in once when the workday starts and out when it ends, with location stamps showing where, or record a punch at each site. If you punch per site, add the drive time between sites back as paid time.
Can a time clock track job costs?
Some can, using job or cost codes that workers switch between as tasks change. Time clocks that record only locations show hours per site but not per task. Decide whether you need per-site or per-task detail before you choose one.
Keep reading
- ConstructionA construction time clock where the foreman scans each worker's QR badge at the gate with any phone. No app for the crew, every site tracked. Free for 3 people.
- LandscapingClock in your landscaping crew at the yard or first stop by scanning QR badges with the crew lead's phone. No app for workers, no hardware. Free for 3 people.
- Crew time clockA crew time clock where the foreman scans each worker's QR badge with one phone: 8 people clocked in in under a minute, no app for the crew. Free for 3 people.
- How to track employee hoursCompare 6 ways to track employee hours by cost, accuracy and buddy-punch risk, build a free Excel timesheet with lunch-break formulas, and know what to keep.
- Timesheet calculatorFree weekly timesheet calculator: enter clock-in and clock-out times with lunch breaks to get total hours, overtime and gross pay. Rounding options too.
- The best time clock apps for construction in 2026The best construction time clock apps of 2026 compared: crew clock-in, GPS, job costing, kiosks and what a 10, 25 or 50-person crew costs each month.
Clock your crew in with one phone.
Print a QR badge for everyone and scan them in and out with any phone or tablet. Free for up to 3 people — try it with your real crew before you sign up.